Showcase Projects
Philip Morris, USA
Richmond, VA
Value
$375,000
Scope
Project consisted of purchasing, fabrication, and installation of complete piping system for vacuum conditioner. Piping systems included 3" stainless steel high-pressure spray. Eight inch steam and condensate piping and water supply piping up to 2" diameter.
Services
Platforms -- Westab Plant
Value
$172,000
Scope
Project consisted of purchasing, fabrication, and installation of ten aluminum access platforms, structural support steel. The platforms were installed in an operating plant at various locations and elevations.
Services
Burley Dryer No. 3 & No. 4 -- Manufacturing Center
Scope
These projects consisted of demolition of two existing Burley tobacco dryers, feeders, associated conveyors, piping, and concrete pads. The installation of two new Burley tobacco dryers manufactured by Proctor-Schwarz and feeders manufactured by Griffin & Company along with new feed and discharge conveyors. Design, fabrications, and installation of intake and exhaust stainless steel ductwork and stacks, tobacco chutes, catwalks, ladders, handrail and monorail systems. Installation of steam, condensate, filtered water, flavor, air, floor drain, and fire protection piping. Concrete work, tile work, roof repairs, ductwork, and piping insulation.
Services
Cut Filler Transport System -- Manufacturing Center
Scope
Project work consisted of demolition of tobacco conveying equipment, modifications to some existing conveyors, and installation of 1,758 L/F of new tobacco conveyors, including design, fabrication, and installation of conveyor support steel and stainless steel tobacco transfer chutes.
Services
Cut Filler Transport Catwalk System -- Manufacturing Center
Value
$781,000
Scope
Project consisted of demolition of existing catwalk and the design, fabrications, and installation of a new duel catwalk system of carbon steel supports, aluminum catwalks and handrails, enclosed with stainless plate for dust protection. The project consisted of 950 L/F of duel catwalk above the top of tobacco storage silos.
Services
Consolidated Services Agreement
Value
$7.8 million
Scope
Provide labor, materials, tools, and supervision to perform miscellaneous projects at all Philip Morris locations in VA. Projects range from toilet repair to design, fabrication, and installation of entire systems. R.S. Harritan furnishes pipefitters, plumbers, sheet metal workers, millwrights and ironworkers (mechanical) on an 'as needed' basis. Various tasks include installation of dryers, cyclones, conveyors, weigh belts, platforms, handrails, catwalks, etc. Piping includes fabrication and installation of all process and HVAC systems. Sheet metal fabrication utilizes carbon steel, stainless steel, galvanized and aluminum. Harritan craftsmen design, fabricate, and install conveyor extensions, product transfer chutes, process and HVAC ductwork, including temperature and humidity control systems. All work is being done in existing facilities and must be coordinated with plant personnel. For the most part, measurements must be taken, drawings produced, fabrication completed, and installation completed in a manner so as not to interfere with plant production or personnel.
Services
E.T. Expansion
Value
$1.5 million
Scope
This project was a fast track expansion for the ET process. The job consisted of a 135,000 C.F.M. air washer system with shop fabrication of dual wall stainless and galvanized ductwork, size 120" x 96" and 0.050 aluminum skin. Also design, fabrication and installation of approximately 2,000 feet of process stainless steel round all welded ductwork for fume and cooling exhaust. Design, fabrication and installation of conveyor hood enclosures, wall fire doors, and transfer chutes. The owner was furnished AutoCAD 14 drawings for this work.
Services
Silo Fall Protection
Value
$972,000
Scope
This project consisted of the design, fabrication and installation of approximately 30,000 feet of aluminum handrail, all welded, for 81 silos and the fabrication and installation of 162 aluminum ladders with hinged gates to access top of silos.
Services
Lump-Sum Contract - Air Washer #8 Replacement -- Opertions Center
Value
$325,000
Scope
Demo of existing air washer coils, casing, concrete base, etc. for installation of new washer consisting of a new pump, heat exchanger and associated piping. Also included were all inter-connecting electrical and control work.
Services
T&M Sheet Metal and Pipefitter Maintenance Support --- Operations Center
Value
$200,000/year
Scope
Support crafts to perform routine day-to-day maintenance operation of building maintenance which includes such items as HVAC office equipment relocation to suit tenant layout, as well as support maintenance of major HVAC plumbing equipment.
Back
to top
|
 |